MINDEN, Nev. — The Douglas County Road Report for county-maintained roads for the week of March 15-29 appears below:

 *All work is tentatively scheduled and subject to change*
 

Continued flood cleanup, Mottsville Lane, Centerville Lane, with delays.

Catch basin and canal at Johnson Lane, work starts Thursday March 16, with detours Wild Horse and Vicky Lane, when north side done the detour will be between Vicky and Wild Horse.

Flood cleanup in the Indian Hills area, pothole patching, sweeping, culvert work.

Continued flood cleanup in Fish Springs.

Regarding Tillman Lane: Douglas County will be addressing the damaged areas in the next couple of weeks and then re-opening the roadway. In the meantime the roadway will remain closed to all traffic.
Full reconstruction and storm drain improvements are currently being planned for construction late this summer.

All work depending on weather conditions.